Re: Cala Corb Walkway

Posted: November 20th, 2019, 8:53 pm
by Shuggie
No work on the walkway this week, it's been stopped. Could we be heading for another white elephant?

Re: Cala Corb Walkway

Posted: November 22nd, 2019, 7:18 pm
by Sunseaker
:sad:

Re: Cala Corb Walkway

Posted: November 22nd, 2019, 7:40 pm
by Tigipaul
Seems crazy to Stop at this late stage when it's nearly connected to Cala Corb,.
Wonder what the contractors are thinking !.
Let's hope it restarts soon. 🙄.
Paul

Re: Cala Corb Walkway

Posted: November 27th, 2019, 2:52 pm
by TrentEnd
Photos taken today. Credit Stokie. Looks like everything has ground to a halt, they've even taken the crane away.

Re: Cala Corb Walkway

Posted: November 27th, 2019, 3:53 pm
by Sunseaker
:sad:

Re: Cala Corb Walkway

Posted: December 24th, 2019, 7:06 pm
by TrentEnd
Progress Report.
Nothing to report.
This project was due to be completed this year but, following GOB's objections, I fear this may go the way of the Carretera General (ME-1), nowhere for years!
My understanding is that the original plan was to build it in concrete from the Hamilton to Cala Corb and build the Cala Corb part in wood, similar to Cala Fons. The change of plan to build it all in concrete seems to be where 'the wheels came off'. I wonder how long it will take them to say, OK we've now got an approximate 70 metre gap in Cala Corb which we'll go back to the original plan and finish in wood.

Re: Cala Corb Walkway

Posted: January 12th, 2020, 9:31 am
by Shuggie
Still no progress
20200111_131138.jpg

Re: Cala Corb Walkway

Posted: January 12th, 2020, 7:44 pm
by peterread543@bt
The Menorca rag https://www.menorca.info/menorca.html gives updates on the problems the last one was from GOB. They are objecting to the concrete path due environmental concerns for the marine life.

Re: Cala Corb Walkway

Posted: February 11th, 2020, 4:55 pm
by TrentEnd
Progress! Workmen back on the job building the seawall before infilling with concrete. As I understand it, the Cala Corb stretch will now be completed as originally planned similar to Cala Fonts rather than continuing in concrete.

Re: Cala Corb Walkway

Posted: February 13th, 2020, 7:56 pm
by TrentEnd
Infilling today.